Network changes are unusual among production changes because the thing you are modifying is the same thing carrying your management session. A bad line in an access list, a VLAN typo, or a routing policy that withdraws the wrong prefix can remove your own path to the device a fraction of a second after you press enter. This checklist is a change-window runbook: capture a baseline, understand the blast radius, arrange a way back in, make the change, verify it, and know exactly how to undo it.
1. Change definition and approval
- The change has a written statement of intent — one paragraph describing what will be different afterwards, in terms of traffic behaviour rather than commands.
- The exact configuration to be applied is pasted into the change record — not a description of it, the literal lines, so the verifier reviews what will actually be typed.
- The change has been peer reviewed by someone who did not write it — network syntax errors are almost never caught by the author, who reads what they meant rather than what they wrote.
- The change window has an explicit end time and a go/no-go decision point — decide in advance the clock time at which you stop troubleshooting and roll back regardless of how close you feel to a fix.
- Approval covers the maintenance window, not just the change — including who is authorised to declare the change failed and call the rollback.
- Dependent teams have been notified with the expected impact window — application, database, and storage owners plan their own freezes around it.
- The change is not stacked with unrelated changes in the same window — bundling three changes means a failure gives you three suspects and no clean rollback.
2. Baseline capture
- The full running configuration is exported and stored off the device — to a git repository or configuration management system, not just the device flash, which is unreachable if the device is unreachable.
- A configuration diff against the last known-good version is clean — any drift you find now is undocumented change that will confuse the post-change comparison.
- Routing and neighbour state is captured before the change — BGP peer counts and prefix counts per peer, OSPF adjacencies, and the default route source.
- Interface counters, error counters, and CDP/LLDP neighbours are recorded — so a post-change increase in CRC errors or a missing neighbour is visible as a change rather than a mystery.
- ARP, MAC address table, and NAT translation counts are captured — a large post-change swing in table size is a strong signal that traffic is taking an unintended path.
- The baseline is saved as a text file with a timestamp, not left in scrollback — terminal buffers get cleared, and the person diffing may not be the person who captured.
# capture into timestamped files before touching anything
for cmd in "show running-config" "show ip bgp summary" "show ip route summary" \
"show interfaces status" "show lldp neighbors"; do
echo "=== $cmd ===" >> baseline-$(date +%Y%m%dT%H%M).txt
done
3. Blast-radius assessment
- Every prefix, VLAN, or service carried by the affected device or link is enumerated — the answer to what breaks must be a list, not a shrug.
- Redundancy has been verified as actually working, not merely configured — check that the standby path currently carries traffic when tested, because a dormant redundant path is often found to have been broken for months.
- Single-homed dependencies are identified — management networks, out-of-band jump hosts, licence servers, and NTP sources are the ones people forget.
- The change is assessed against maintenance-affecting traffic — backups, batch replication, and scheduled reporting jobs that run during the quiet window you chose precisely because it is quiet.
- Impact on stateful devices is understood — firewall session tables, load balancer connection state, and NAT translations do not survive a path change, so existing long-lived flows will drop even if routing converges.
- The failure mode is predicted in writing — state whether a mistake causes a hard outage, a partial blackhole, or an asymmetric path, because each needs a different verification.
4. Out-of-band access
- Console or out-of-band access is tested and open before the first command — not tested last week, tested now, in a second window, with a prompt visible.
- The out-of-band path does not traverse the device being changed — a serial console server reachable only through the production network is not out of band.
- Credentials for the out-of-band path are on hand and verified — including a local fallback account, because the change may cut reachability to the RADIUS or TACACS+ server.
- A commit-confirm or scheduled rollback timer is armed where the platform supports it — the device reverts to the previous configuration automatically unless you confirm within the timer, which converts a lockout from an outage into a short blip.
- On platforms without commit-confirm, a reload timer is set before applying — schedule a reload to the saved configuration, then cancel it once verification passes.
- The configuration is not saved to startup until verification is complete — an unsaved change is undone by a power cycle, which is your last-resort rollback.
! IOS-style safety net: device reboots to saved config in 10 minutes
reload in 10
! ...apply change, verify reachability...
reload cancel
5. Applying the change
- Changes are applied in an order that keeps the management path alive longest — add the new permit before removing the old one, bring the new adjacency up before tearing the old one down.
- Access list edits are made by building a new named list and swapping it atomically — editing an applied list line by line briefly leaves the device in a state neither old nor new, which is when the deny-any at the end bites you.
- Configuration is pasted from the reviewed change record, not retyped — retyping introduces exactly the single-character errors that peer review was meant to eliminate.
- Terminal logging is enabled so the entire session is captured — you will want the exact transcript during the post-incident review, and you will not remember it accurately.
- Each discrete step is verified before the next is applied — batching ten steps and verifying once means the failure is attributed to the wrong step.
- The verifier confirms reachability from an independent location after each step — the engineer’s own session can survive a change that breaks everyone else’s path.
- Nothing is saved to startup configuration until the verification section passes in full.
6. Verification
- Control-plane state is diffed against the baseline — same BGP peer count, same prefix counts within an expected delta, same adjacencies, no new flapping.
- Data-plane reachability is tested from a real client, not from the device — a router can ping a destination through a management VRF that user traffic never uses.
- Both directions of the path are tested — asymmetric routing frequently survives a one-way ping test and then breaks any stateful firewall in the path.
- Path MTU is validated with a large do-not-fragment packet — new tunnels and encapsulations silently shave bytes, and the symptom is that small requests work while large responses hang.
- Application-level health is confirmed, not just ICMP — check the actual service, because ICMP is often permitted where TCP is not.
- Error counters are checked for increases since the baseline — CRC errors, input drops, and output discards appearing after the change point to a duplex, optics, or buffer problem introduced by it.
- Monitoring and alerting show green from the monitoring system’s own perspective — confirm the monitoring system can still reach the device, since a change that breaks polling makes everything look quiet.
- A defined soak period is observed before declaring success — at least fifteen minutes of steady state, long enough for routing to settle and for periodic jobs to exercise the path.
7. Rollback
- The rollback procedure is written out as commands before the change begins — improvising a rollback under pressure is how a small outage becomes a long one.
- Rollback has been tested in a lab or on a non-production peer where the change is non-trivial — especially for anything involving routing policy or spanning tree.
- The rollback decision criteria are objective — a named metric and a threshold, so the decision does not depend on the changer’s optimism at 2am.
- Restoring the previous configuration is known to be sufficient — if the change caused neighbours to reconverge, clear routing adjacencies and stateful sessions explicitly rather than assuming they recover.
- The rollback is verified with the same verification steps as the change — a partial rollback that restores reachability but leaves policy half-applied is worse than either state.
- A hard time limit is set on troubleshooting before rollback is mandatory — write the clock time on the bridge at the start of the window.
8. Closure and documentation
- The post-change configuration is saved and exported to the configuration repository — the source of truth must match the device before the next change starts from it.
- Network diagrams, IPAM entries, and the CMDB are updated in the same window — documentation updated later is documentation not updated.
- Monitoring is updated for any new interfaces, peers, or thresholds — a link added today with no alerting is a link that fails silently in six months.
- The change record is closed with the actual outcome, including anything unexpected — near misses are the most valuable content in a change record.
- Firewall and access list changes are recorded with a review date — temporary permits become permanent unless something forces them to be revisited.
- Lessons that would change the runbook are fed back into it immediately — while the detail is fresh, not at the retrospective.
Sign-off
| Area | Reviewer | Date | Outcome |
|---|---|---|---|
| Change definition and approval | Pass / Pass with actions / Fail | ||
| Baseline capture | Pass / Pass with actions / Fail | ||
| Blast-radius assessment | Pass / Pass with actions / Fail | ||
| Out-of-band access | Pass / Pass with actions / Fail | ||
| Applying the change | Pass / Pass with actions / Fail | ||
| Verification | Pass / Pass with actions / Fail | ||
| Rollback | Pass / Pass with actions / Fail | ||
| Closure and documentation | Pass / Pass with actions / Fail |
The out-of-band access section must be a full Pass before the window opens; any other section may close with a dated follow-up ticket and a named owner.
Related checklists